Stayton Keeps Annexing Land for New Homes. The Sewer Pipes Set the Pace.

October 29, 2026

"At maximum capacity and cannot currently accommodate additional sewer flows." That line comes from an October 5, 2026 City of Stayton Public Works memo. It describes the existing sanitary sewer system downstream of a proposed 101-lot neighborhood on E Pine Street, "starting at E Marion Street and continuing west."

If you're comparing Stayton with Salem, Silverton, or Sublimity and expecting a steady stream of new construction, that memo matters more than any annexation headline. In Stayton, land is easier to find than sewer capacity. The pace of new homes depends on a multi-phase trunk line project. Its own funding paperwork expects the deadline to slip, and each new house pays a city wastewater development charge on top of the other fees.

A 101-lot plan that depends on capacity downstream

The E Pine Street proposal comes from Ross Bochsler and Kardboard Box, LLC. It would annex about 38.96 acres into the city, apply Medium Density Residential zoning, and add a conceptual master plan for 101 single-family lots with water quality facilities and open space. The Stayton Planning Commission recommended approval after its August 31, 2026 hearing. The City Council held its public hearing on September 21 and kept the written record open through October 5.

Sewer questions came up during that open-record period. The October 19, 2026 council packet shows staff revised the findings to reflect "the City's ongoing evaluation of downstream sewer capacity" and still recommended approval of Ordinance No. 26-009. The packet also says that if the first vote is not unanimous, the ordinance comes back for a second consideration on November 2, 2026.

A council vote to annex settles the city limits and zoning for the 38.96 acres. It does not settle sewer service. Under the Public Works memo, any development application on the property must include design calculations showing the city system has enough capacity for the added flows, along with a workable route to an approved point of discharge. The memo says the City is re-evaluating that sub-basin to see whether capacity has opened up after recent work on Ida Street.

The Ida Street fix, phase by phase

The City's 2021 Wastewater Facilities Planning Study modeled the collection system and found pipe-capacity limits. Its top-priority upsizing list started with Jetters Way and W Ida Street. The study also notes that Sublimity's collection system flows into Stayton's system and on to Stayton's treatment plant, so growth in both towns draws on the same downstream pipes.

Here is how the work has gone so far:

  1. Phase 1, finished by late 2023. Marion County's federal recovery fund report describes a $500,000 project that replaced a 21-inch pipe with a 30-inch pipe, running from Jetters Way near the Fire District building to a manhole in front of 1207 Ida Street. The report lists it as complete as of November 2023.
  2. Phase 2, finished. Stayton's 2025–27 approved budget reports the second phase of the Ida Street 30-inch trunk line as complete.
  3. Phases 3 and 4, now in design. On September 21, 2026, the council awarded AKS Engineering and Forestry $639,953 to design two upsizing projects, one on N Evergreen Avenue and one on W Ida Street. The scope includes about 1,300 feet of new 21-inch trunk sewer in W Ida Street, about 400 feet in N First Avenue, and preliminary design of a crossing at the Salem Ditch.

The Pine Street memo says Phase 3 is "scheduled for 2027." The grant paperwork suggests that date could move. According to the September 21 staff report, the $3 million Oregon Business Development Department grant behind this work was signed in October 2024 with a June 30, 2025 completion date. It was later extended to June 30, 2027, and the report says another extension to June 30, 2028 "will likely be requested" because of environmental permitting and timing. The next stretch north of the Salem Ditch is funded through an $800,000 state Clean Water loan signed July 10, 2026, which is 50 percent forgivable.

Capacity limits extend to the treatment plant too. The 2021 Wastewater Facilities Planning Study rated its SBR basins at 4.1 million gallons per day, against a need of 4.09 at the time and a projected 4.54 by 2040. It names the Three Basin Rule, the state limit on discharges into the North Santiam, as the cap.

Other projects on the edge of town are stuck on the same issues

Pine Street isn't the only case. Nearly every residential proposal in current city records is held up by sewer or stormwater:

Project Size Where it stands
E Pine Street, Kardboard Box, LLC ~38.96 acres, 101 conceptual lots Council decision on the October 19 agenda. Downstream sewer capacity still under evaluation
Phillips Estates III, 1601 Oriole Street 7.11 acres, 22 lots Planning Commission approved it July 27, 2026. Developer appealed the conditions, and staff recommended continuing the hearing to November 2 over stormwater retention and drainage
Golf Club Road, Brownstone Homes ~60 acres annexed Earlier 126-unit application withdrawn. No replacement subdivision filed
Shaff Road 17 acres Planning Commission recommended Low Density rather than the High Density requested. A sewer capacity analysis is required

Our Town reported that when the Golf Club Road land was annexed, City staff said no replacement subdivision application had been submitted. For the Shaff Road parcel, the City's draft order says the property isn't yet on city utilities and that a sewer connection requires a capacity analysis. The Santiam Water Control District says the Salem Ditch is at capacity and any discharge into it needs district approval.

Across these four projects, a few hundred potential homes are tied up in hearings, withdrawn applications, and capacity studies, and none of them is a finished lot yet.

What the pipes cost each new house

Stayton's fee schedule effective July 6, 2026 lists system development charges for a typical single-family home on a new street, standard ¾-inch meter:

  • Wastewater: $12,072
  • Water: $4,260
  • Stormwater: $3,785
  • Transportation: $7,649
  • Parks: $4,092
  • Total: $31,858

Wastewater is the largest single charge, about 38 percent of the total. On top of that, the City collects a $1.70-per-square-foot school construction excise tax for the North Santiam School District. For an 1,800-square-foot house, that adds $3,060, so the house carries close to $35,000 in charges before construction begins. The City adopted a revised wastewater and transportation SDC methodology on August 4, 2025.

The system also shows up in monthly bills after closing. Effective July 1, 2026, Stayton raised residential water, wastewater, and stormwater rates by 3 percent each. The residential wastewater flat rate is now $77.61 a month, and the typical ¾-inch water base charge is $36.76 before usage, according to the City's utility rate handout.

What new construction sells for in this part of the county

No published report breaks out Stayton alone, but the Willamette Valley Multiple Listing Service's September 2026 report tracks a Marion County area separate from the Salem and Keizer districts. That's the closest available view of what Stayton buyers are choosing between.

Marion County area, WVMLS September 2026 report New construction, trailing 12 months Resale, 2026 year to date
Sales 186 618
Average sale price $489,071 $528,227
Average square footage 1,800 1,791
Average price per square foot $273 $301
Average days on market 124 110
Active listings 59 298

These are averages, not medians, and the two columns cover different time periods, so treat them as general direction rather than an exact comparison. Even so, new homes in this part of the county averaged less per square foot than resales and took longer to sell, with 59 new-construction listings on the market. For a Stayton buyer, the supply that exists today is what you're choosing from. The fee figure above is a good benchmark too. At $31,858, the SDC total equals about 6.5 percent of the area's average new-construction price.

Questions to bring to a Stayton new-build listing

Since capacity varies by sub-basin, the useful questions are specific to the lot:

  • Is the lot on a recorded final plat, or is the subdivision still in land-use or engineering review?
  • Are the system development charges already paid, and are they included in the quoted price?
  • If the subdivision is not built yet, has the developer shown sewer capacity under the City's design-calculation requirement?
  • Is the lot on a new street, which uses the $3,785 stormwater charge, or an existing street, which uses $2,652?

Quick answers

Does annexation mean homes are coming soon? Not necessarily. Annexation brings land into the city and sets its zoning. Building homes still requires engineering review, land-use approval, and proof of sewer capacity, as the Pine Street memo shows.

When will the Ida Street sewer work be finished? The City's memo lists Phase 3 improvements for 2027. The grant funding it has a June 30, 2027 deadline, and staff expect to request an extension to June 30, 2028.

Does any of this affect existing homes? Existing homeowners pay the monthly rates, including the 3 percent increase that took effect July 1, 2026. The system development charges apply to new construction.

This post is general information, not legal, tax, or financial advice. Fees and rules change, so please confirm the details of your own purchase with the City of Stayton and the right professionals.

If you're weighing a Stayton new build against a resale and want to know how far along a subdivision really is before you commit, Jenny Morrow can walk you through the city records and the questions that matter for your lot. Let's connect.

Dedicated Representation

Jenny believes great results begin with understanding each client’s goals. She provides thoughtful guidance and strategic support throughout every step of the process. Clients trust her to deliver an experience that is both smooth and successful.